Additional Temporary Relief Measures for Property Sector due to Coronavirus Disease 2019 (COVID-19) Pandemic
The Government on October 8th, announced additional temporary relief measures for property developers affected by disruptions to construction timelines resulting from the COVID-19 pandemic. This is in addition to the temporary relief measures announced on 6 May 2020. These temporary relief measures do not affect the other existing residential property market cooling measures which remain relevant to ensure that private residential property prices are broadly consistent with economic fundamentals.
The additional temporary relief measures, to be implemented with immediate effect, are:
(i) Extension of the Project Completion Period (PCP) by a further 6 months for residential, commercial and industrial development projects;
(ii) Extension of time by a further 6 months for the commencement and completion of the residential development projects in relation to the remission of the Additional Buyer’s Stamp Duty (ABSD) for housing developers (Details on the remission of ABSD for housing developers are provided under the Stamp Duties (Housing Developers) (Remission of ABSD) Rules 2013 and the Stamp Duties (Non-Licensed Housing Developers) (Remission of ABSD) Rules 2015); and
(iii) Extension of the PCP by up to a further 6 months for residential development projects under the Qualifying Certificate (QC) regime for foreign housing developers.
While almost all construction projects have restarted, the full resumption of on-site operations remains a challenge with workers being placed under quarantine if they have come in close contact with a positive COVID-19 case, and worksite practices requiring redesign for safe distancing. These public health measures are necessary to prevent the industry from going into lockdown again, but they continue to affect construction timelines.
All qualifying housing developers will continue to be subject to the prevailing ABSD regime, albeit with a further 6-month extension of the remission condition timelines for commencement and completion of the residential development projects. There is no further extension of the remission condition timeline for the sale of all housing units in the residential development project.
Contractors and developers have raised concerns regarding the additional costs and financial penalties in contracts between stakeholders that may be incurred as a result of delays due to the COVID-19 pandemic. With these additional support measures, the Government expects developers to continue to similarly provide relief and support to their main contractors. The Government will also continue to closely monitor the impact of the COVID-19 pandemic on the progress of work within the construction industry, and on the property sector. The Government will implement additional relief measures to support the stakeholders as necessary, and ensure that no stakeholder bears an undue share of the burden imposed by the COVID-19 pandemic.
Additional Temporary Relief Measures for Private Residential Development Projects
PCP. The PCP for qualifying residential development projects on Government sale sites, or on land which was directly alienated or had their lease renewed by the Singapore Land Authority (SLA), will be extended by a further 6 months.
The conditions to be met to qualify for the extension of the PCP remain the same (as per the temporary relief measures announced on 6 May 2020), and are as follows:
(i) The land was awarded on or before 1 June 2020, or the land was directly alienated or had their lease renewed by SLA on or before 1 June 2020; and
(ii) The original timeline for completion of the residential development expired on or after 1 February 2020.
Eligible developers will be notified by the respective agencies. No application is necessary.
ABSD. Under the ABSD regime, developers are to commence and complete the residential development, and sell all housing units in the residential development project within the specified timelines, failing which they will be subject to the ABSD on the purchase of the land. The specified timeline for commencement of housing development is 2 years from the purchase of the land for all housing developers. The specified timelines for completion of housing development and sale of all housing units are 5 years from purchase of the land for licensed developers (those who construct more than 4 housing units), and 3 years from purchase of the land for non-licensed developers (those who construct no more than 4 housing units). Under the temporary relief measures announced on 6 May 2020, the specified commencement, completion and sale timelines were extended by 6 months, subject to conditions.
Under the additional temporary relief measures, the specified commencement and completion timelines will be extended by a further 6 months, for qualifying residential development projects. There is no further extension of the specified timeline to sell all housing units in the residential development project.
The conditions to be met to qualify for the extension of the specified timelines for commencement of residential development remain the same (as per the temporary relief measures announced on 6 May 2020), and are as follows:
(i) The land was purchased on or before 1 June 2020; and
(ii) The original timeline for commencement of the residential development expired on or after 1 February 2020.
The conditions to be met to qualify for extension of the specified timeline for completion of residential development remain the same (as per the temporary relief measures announced on 6 May 2020), and are as follows:
(i) The land was purchased on or before 1 June 2020; and
(ii) The original timeline for completion of the residential development expired on or after 1 February 2020.
Eligible developers will be granted the extension automatically. No application is necessary.
QC. Under the QC regime, developers subject to the QC rules are to complete construction of all housing units in a residential development project within 5 years from the date of issue of the QC or the collective sale order, and dispose of all housing units within 2 years from the issue of Temporary Occupation Permit or Certificate of Statutory Completion. Under the additional temporary relief measures, developers applying to extend their existing completion deadline will be granted a further waiver of extension charges of up to a total of 6 months. This will also apply to other SLA approvals requiring the completion of all units in the residential development. There is no further waiver of extension charges to extend the existing deadline to dispose of all housing units in the residential development project.
The conditions to be met to qualify for the waiver of extension charges to extend the completion deadline remain the same (as per the temporary relief measures announced on 6 May 2020), and are as follows:
(i) The QC or SLA approval requiring the completion of all units in the residential development was issued on or before 1 June 2020; and
(ii) The original timeline for completion of the residential development expired on or after 1 February 2020.
Eligible developers can write to SLA’s Land Dealings Approval Unit (LDAU) by 1 December 2020 to apply. Developers which had already applied for and obtained an extension of their existing completion deadlines under the temporary relief measures announced on 6 May 2020 will automatically be granted the further 6-month waiver of extension charges, and will be notified of their new deadlines by LDAU.
Commercial and Industrial Development Projects
PCP. The PCP for qualifying commercial and industrial development projects on Government sale sites, or on land which was directly alienated or had their lease renewed by SLA, will be extended by a further 6 months.
The conditions to be met to qualify for the extension of the PCP remain the same (as per the temporary relief measures announced on 6 May 2020), and are as follows:
(i) The land was awarded on or before 1 June 2020; or the land was directly alienated or had their lease renewed by SLA on or before 1 June 2020; and
(ii) The original timeline for completion of the development expired on or after 1 February 2020.
Eligible developers will be notified by the respective agencies. No application is necessary.